Construction begins on WIS 190 in Waukesha, Milwaukee Cos.

MILWAUKEE (WITI) -- Crews began work this week on WIS 190 (Capitol Drive), from Brookfield Road to WIS 100 in Waukesha and Milwaukee Counties. This project will complete work that began last year on this 5-mile segment of roadway.

The work this construction season consists of finishing permanent pavement markings, permanent signage, concrete sidewalk, retaining walls, asphalt and concrete repair, and miscellaneous storm sewer and signal work.

WIS 190 will be open to traffic, with shoulder closures and single lane closures throughout the duration of the project. Occasional night work will limit traffic to one lane from 7pm – 6am.

The contractor, Payne and Dolan, is expected to complete work by late June 2013, weather permitting.