MILWAUKEE -- Construction is really picking up -- with changes coming to I-94 and the Zoo Interchange. Ryan Luck with the Wisconsin Department of Transportation joins FOX6 WakeUp to talk about everything that is going to impact your commute.

Friday, December 9 (setting girders for Wisconsin Ave bridge over I-41 North)

  • I-41/894 North full closure at Greenfield Avenue - 10PM - 7AM
  • I-94 West to I-41 North system ramp closure - 10PM - 7AM

Sunday, December 11th

    • I-94 East full closure at Moorland Road - 11PM - 5AM.

This closure is needed for the switch that will make the 84th Street exit ramp inaccessible from I-94 East. This isĀ dependent on weather conditions.

Monday, December 12

  • I-41/894 Northbound full closure at Greenfield Avenue - 11PM - 4:30AM
  • I-94 West to I-41 North system ramp closure - 11PM - 4:30AM

Tuesday, December 13

  • I-41/894 Northbound full closure at Greenfield Avenue - 11PM - 4:30AM
  • I-94 West to I-41 North system ramp closure - 11PM - 4:30AM

Friday, December 16 (setting girders for Wisconsin Ave over I-41 South)

  • I-41 South full closure at Watertown Plank Road - 10PM - 7AM
  • I-41 South double left lane closure - 8PM - 10PM and 7AM - 9AM